Pulaski Wastewater Treatment Plant Improvements
Project Description:
This project consisted of the improvements of the Pulaski WWTP to renovate existing facilities and to handle peak flows. Two new fine screens were installed at the existing Headworks and a new final clarifier was constructed. A new solids holding tank was constructed to hold solids from the water treatment plant sedimentation basis that were previously pumped through the plant. New dewatering equipment and a solids storage area were also constructed with the project.
Project Name: Wastewater Treatment Plant Improvements
Utility Name and Location: City of Pulaski, Pulaski, Tennessee
Key Personnel: J. Gregory Davenport, P.E., Stephen C. Lee, P.E., Dwight Phillips, P.E. (Electrical Engineer)
Construction Cost: $9,510,000
Date of Completion: Expected Summer 2025
Engineering Services: Planning, Detailed Design, Bidding and Award, Construction Administration, and Resident Observation